PENGARUH PENAMBAHAN TITIK GROUND ROD TERHADAP NILAI TAHANAN PENTANAHAN TOWER TRANSMISI SUTT 70kV TES-PEKALONGAN

Penulis

  • Rhenol Alexander Siboro Universitas Pembangunan Panca Budi
  • Siti Anisah Universitas Pembangunan Panca Budi

Kata Kunci:

grounding resistance, ground rod, transmission tower

Abstrak

The grounding system is an important part of the installation of the High Voltage Overhead Line (SUTT) transmission tower, which serves to channel the interference current to the ground to maintain human safety and equipment reliability. A low grounding resistance value is needed for the protection system to work optimally. This study aims to analyze the effect of the addition of ground rod points on the grounding resistance value in the 70kV TES-PEKALONGAN SUTT transmission tower. Measurements are made directly using an earth tester. The measurement results show that the addition of ground rod points can significantly reduce the grounding resistance value. Thus, increasing the number of grounding points can be one of the technical solutions to improve the performance of the grounding system on the electricity transmission network.

Unduhan

Data unduhan belum tersedia.

Referensi

Departemen Energi dan Sumber Daya Mineral. (2000). Persyaratan Umum Instalasi Listrik (PUIL 2000). Jakarta: Direktorat Jenderal Ketenagalistrikan.

Departemen Energi dan Sumber Daya Mineral. (2011). PUIL 2011. Jakarta: Direktorat Jenderal Ketenagalistrikan.

IEEE. (2000). IEEE Std 80-2000: Guide for Safety in AC Substation Grounding. New York: Institute of Electrical and Electronics Engineers.

IEEE. (2013). IEEE Std 81-2012: Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials. New York: Institute of Electrical and Electronics Engineers.

IEC. (2010). IEC 62305: Protection Against Lightning. Geneva: International Electrotechnical Commission.

IEC. (2015). IEC 61936-1: Power Installations Exceeding 1 kV AC. Geneva: International Electrotechnical Commission.

PT PLN (Persero). (2010). Buku Pedoman Konstruksi SUTT 70 kV. Jakarta: PT PLN (Persero).

PT PLN (Persero). (2014). Pedoman Pemeliharaan Sistem Pentanahan Jaringan Transmisi. Jakarta: PT PLN (Persero).

PT PLN (Persero). (2018). Standar Konstruksi Tower Transmisi Tegangan Tinggi. Jakarta: PT PLN (Persero).

Hutauruk, T. S. (1991). Grounding System. Jakarta: Erlangga.

Unduhan

Diterbitkan

30-04-2026

Cara Mengutip

Rhenol Alexander Siboro, & Siti Anisah. (2026). PENGARUH PENAMBAHAN TITIK GROUND ROD TERHADAP NILAI TAHANAN PENTANAHAN TOWER TRANSMISI SUTT 70kV TES-PEKALONGAN. Jurnal Nasional Teknologi Komputer, 6(2), 1059–1079. Diambil dari https://publikasi.hawari.id/index.php/jnastek/article/view/434

Terbitan

Bagian

Artikel